The Banks Progress

Reports for The Banks Project

Project partners, developers and contractors report their progress to create The Banks Project Reports. In particular, each report covers planning, design and construction progress for the various phases. Appendices document results for each period in budget together with print and electronic media mentions. Reports for The Banks Project also document economic inclusion results. Click on the links below to access construction and developer project reports, in addition to accompanying tables and summaries.

The Banks Progress: Quick Stats Through June 30, 2020

SAFETY
873,542 Phase I, II, IIIA and IIIB Public infrastructure construction hours worked without a lost-time incident.
995,175 Phase IIA and IIB, and AC Hotel Developer construction safety hours.

BUDGET
65.6% of Phase IIIB budget expended. Phase IIIB of the Public Partnership’s construction projects remains within budget.

INCLUSION
28.9% Overall construction participation on Phases I, II, IIIA and IIIB by Small Business Enterprises (vs. 30% goal).
14.13% Combined Minority and Female workforce participation for Phase I, II, IIIA and IIIB (vs. 10% goal).

SCHEDULE
All critical milestones for Phase IIIB of the public infrastructure construction have been met.

Supporting websites

Explore The Banks developer website here.

Learn more about the Andrew J. Brady ICON Music Center here, a state-of-the-art music venue that will feature a diverse mix of up-and-coming artists as well as longtime favorites. The year-round facility will host up to 170 events annually and will include an outdoor stage for concerts and festivals in the park adjacent to the venue. The ICON’s proximity to The Banks restaurants, retail and hotels will make attending a concert a park-once experience.