the banks public partnership cincinnati
the banks cincinnati
the banks cincinnati construction

The Banks Progress

Reports for The Banks Project

Project partners, developers and contractors report their progress to create The Banks Project Reports. In particular, each report covers planning, design and construction progress for the various phases. Appendices document results for each period in budget together with print and electronic media mentions. Reports for The Banks Project also document economic inclusion results. Click on the links below to access construction and developer project reports, in addition to accompanying tables and summaries.


The Banks Progress: Quick Stats Through March 31, 2024

BUDGET
97.9% of Phase IIIC budget expended and the Public Partnership’s construction projects remains within budget.

SAFETY
982,694.5 Public infrastructure construction hours worked without a lost-time incident for all phases.

1,154,004.25 Developer construction safety hours for all phases.

INCLUSION
27.6% Overall construction participation for all phases by Small Business Enterprises (vs. 30% goal).

20.32% Combined Minority and Female workforce participation for Phase IIIC.

SCHEDULE
All critical milestones of the public infrastructure construction have been met.

Current

2024 Reports


Archives

2023–2018 Reports

2017–2012 Reports

2012–2008 Reports

Supporting websites

Explore The Banks developer website here.

Learn more about the Andrew J. Brady Music Center here, a state-of-the-art music venue that will feature a diverse mix of up-and-coming artists as well as longtime favorites. The year-round facility will host up to 170 events annually and will include an outdoor stage for concerts and festivals in the park adjacent to the venue. The Brady Music Center’s proximity to The Banks restaurants, retail and hotels will make attending a concert a park-once experience.

Scroll to Top